MV. SINAR BANDA
JOB ACCOMPLISHED IN 6 DAYS AHEAD OF SCHEDULE WITH 0 INCIDENT Docking 06-11-2018 02.00 am Start work 06-11-2018 08.00 amUndocking 12-11-2018 3.00 pmShip Type :Container VesselSize :147 meter (L), 25 meter (W), 13.70 meter (H)
On 12th November 2018, PT. Waruna Shipyard Indonesia cherish a great achievement of good teamwork with PT. Samudera Indonesia Shipping on the completion of work and undocking of MV. SINAR BANDA within 6 working days, which is ahead from original schedule of 12 days. MV. SINAR BANDA is one of the vessel owned by PT. Samudera Indonesia Shipping Company which is undergoing her intermediate survey (IS). She arrived at PT. Waruna Shipyard Indonesia on 05th November 2018 with last discharge port at Belawan
PLANNING AHEADPlanning was done way ahead with our Project Planning Control Team, Project Manager and Production Team. Major concern was for governor service, which is done in house at PT. Waruna Shipyard Indonesia. Following the Steering Gear Service and Generator intercooler M/E 1 pcs c/w condenser for cleaning and intercooler A/E 3 nos for cleaning to be carried out at our workshop. Replacement was done for all sea water cooling pipe, fresh water pipe including servicing all valve and overboard system, which also covers boilers and auxiliary equipment and their valves and gauges. Retrofitting of bridge wing platform (port/stbd) and fabricating working platform for lifeboat maintenance. Treatment of external hull was specified as full blast of topside, following by spot and light sweep blast of the underwater area including maintenance of all hatch cover. Electrical and Mechanical System service for alternator cleaning and heating, was also done within the docking period.
TEAM EFFORT This project was monitored closely on 24 hours basis by both Owner and Shipyard Team. For shaft bounding and clearance shaft, the work was assisted by technical/ service engineer from Holland. COMPLEX CONNECTION MV. SINAR BANDA departed ahead of schedule of with cohesive teamwork between PT. Waruna Shipyard Indonesia and Owner Superintendent team to deliver the work ahead of schedule with Zero Incident although we were faced by bad weather. And She will be loading her Cargo straight forward at Belawan Port after undocking. We look forward to be inclusive in all our clients need and we will ensure the betterment towards both organizational goals in welcoming MV. SINAR SOLO this coming December 2018.
>> █